Birla Trimaya Phase 4 Project Schedule Plan 2026 Update
As of 2026, Birla Trimaya Phase 4 has received RERA approval (PRM/KA/RERA/1250/303/PR/290126/008436), and the EOI phase has started. The construction work will begin with the Sub-Structure and foundation work in late 2026. After that, the Super-Structure work of the G+14 towers will continue from 2027 to 2029.
The Finishing Works will be done between 2030 and 2031. At the same time, Internal Infrastructure work, like plumbing, wiring, and basic systems, will be completed. External Infrastructure such as power supply and sewage systems, will also be finished during this period. The amenities in the 52-acre township, including the 2.5-acre man-made lake and the 60,000 sq. ft. clubhouse, are planned to be ready before the final possession in December 2031.